Akkuyu nuclear plant"s first power unit 95% complete, says Turkish minister
Region
- 04 January, 2026
- 17:13
Add Report.az to preferred Google sources
Stay up to date with the top news!
The first power unit of the Akkuyu Nuclear Power Plant is 95% complete, Türkiye's Minister of Energy and Natural Resources Alparslan Bayraktar said on Kanal 7, Report informs.
Bayraktar noted that the work was initially planned to be completed by April 2025, but delays occurred due to the pandemic and political obstacles related to the procurement of certain equipment.
"At present, all our efforts are focused on completing the construction of the first reactor. The work is now about 95% finished, and the start of electricity generation is planned for 2026. We are working closely in this direction with Russia and the Rosatom company," the minister said.
Türkiyənin Energetika Nazirliyi: "Akkuyu" AES-nin birinci enerji blokunun 95 faizi hazırdır
Минэнерго Турции: Первый энергоблок АЭС "Аккую" готов на 95%
Latest News
16:29
Gunel Badalova elected Vice President of International Ski Mountaineering Federation
Individual sports
16:12
Yemeni government forces say they repel lengthy Houthi attacks in Taiz
Other countries
15:50
Video
Military pilots from Azerbaijan, UAE successfully complete their objectives as part of joint exercises
Military
15:25
Photo
AzerGold participates in 6th Rebuild Garabagh exhibition
Industry
15:18
IMF members call for more support amid war shocks, 'advanced intelligence' risks
Other countries
14:47
Photo
NATO training course concludes in Baku
Military
14:27
Indonesian cuisine showcased in Baku
Foreign policy
14:15
Mongolia becomes new donor to World Bank's fund for poorest countries
Other countries
13:55
Photo
Azerbaijan mulls co-op with IMF, ADB in Bangkok
Finance